Projects
CATEGORY:
Buildings/Civil works
STATUS:
ongoing
CLIENT:
NMDC Limited
VALUE:
340.18 Cr
FEATURES:
87,775 Sqm across residential towers, hostels & sports complex; EPC Mode-III
LOCATION:
Kirandul, Chhattisgarh
COMPLETED DATE:
--
Development of a new township near the Arvind College area and construction of residential towers in the existing NMDC Kirandul Township, Chhattisgarh, on EPC Mode-III basis.
The project was appointed on 7 May 2026 with a completion period of 18 months, covering a total built-up area of 87,775 Sqm.
| Building Block | No. of Blocks | Area / Block (Sqm) | Total Area (Sqm) |
|---|---|---|---|
| Type-III Residence (S+10) | 5 | 8,600.11 | 43,000.55 |
| Type-V Residence (S+10) | 1 | 11,289.31 | 11,289.31 |
| Transit & Apprentice Hostel (G+10) | 1 | 8,235.28 | 8,235.28 |
| Staff Hostel (S+10) | 1 | 6,104.82 | 6,104.82 |
| Executive Studio Apartment (S+10) | 1 | 8,713.96 | 8,713.96 |
| Executive Trainee Hostel (S+10) | 1 | 6,141.93 | 6,141.93 |
| Shopping & Sport Complex | 1 | 3,139.46 | 3,139.46 |
| Electrical Substation | 1 | 1,150.00 | 1,150.00 |
| Total Area | 87,775.31 |

Development of a new township near the Arvind College area and construction of residential towers in the existing NMDC Kirandul Township, Chhattisgarh, on EPC Mode-III basis.
The project was appointed on 7 May 2026 with a completion period of 18 months, covering a total built-up area of 87,775 Sqm.
| Building Block | No. of Blocks | Area / Block (Sqm) | Total Area (Sqm) |
|---|---|---|---|
| Type-III Residence (S+10) | 5 | 8,600.11 | 43,000.55 |
| Type-V Residence (S+10) | 1 | 11,289.31 | 11,289.31 |
| Transit & Apprentice Hostel (G+10) | 1 | 8,235.28 | 8,235.28 |
| Staff Hostel (S+10) | 1 | 6,104.82 | 6,104.82 |
| Executive Studio Apartment (S+10) | 1 | 8,713.96 | 8,713.96 |
| Executive Trainee Hostel (S+10) | 1 | 6,141.93 | 6,141.93 |
| Shopping & Sport Complex | 1 | 3,139.46 | 3,139.46 |
| Electrical Substation | 1 | 1,150.00 | 1,150.00 |
| Total Area | 87,775.31 |